  • Government of Andhra Pradesh allotted 241.50-acre (including 80 feet road) land located at Gambheeram Village of Anandapuram Mandal to IIM Visakhapatnam.
  • Construction of the boundary wall for the site was completed.
  • The site was handed over by Andhra Pradesh State government to IIM Visakhapatnam on March 8, 2018.
  • DPR approved by GoI on September 17, 2018, with a total estimated cost of Rs.807.76 crore and Rs 445 crore for Phase-I.
  • The Institute has appointed M/s. Arcop Associates Pvt. Ltd as an Architect, NBCC (India) Ltd as a Project Management Consultant (PMC) and Shapoorji & Pallonji as a construction agency for the proposed Permanent Campus.
  • Permanent Campus Photos

Campus Construction Progress - 15.02.2024
Campus Construction Progress - 30.01.2024
Campus Construction Progress - 18.01.2024
Campus Construction Progress - 01.01.2024
Campus Construction Progress - 15.12.2023
Campus Construction Progress - 03.12.2023
Campus Construction Progress - 15.11.2023
Campus Construction Progress - 31.10.2023
Campus Construction Progress - 18.10.2023
Campus Construction Progress - 02.10.2023
Campus Construction Progress - 18.09.2023
Campus Construction Progress - 03.09.2023
Campus Construction Progress - 02.08.2023
Campus Construction Progress - 27.06.2023
Campus Construction Progress - 31.05.2023
Campus Construction Progress - 11.05.2023
Campus Construction Progress - 22.04.2023
Campus Construction Progress - 04.04.2023
Campus Construction Progress - 16.03.2023
Campus Construction Progress - 04.03.2023
Campus Construction Progress - 19.02.2023
Campus Construction Progress - 03.02.2023
Campus Construction Progress - 17.01.2023
Campus Construction Progress - 31.12.2022
Campus Construction Progress - 15.12.2022
Campus Construction Progress - 30.11.2022
Campus Construction Progress - 16.11.2022
Campus Construction Progress - 02.11.2022
Campus Construction Progress - 19.10.2022
Campus Construction Progress - 30.09.2022
Campus Construction Progress - 19.09.2022
Campus Construction Progress - 02.09.2022
Campus Construction Progress - 20.08.2022
Campus Construction Progress - 01.08.2022
Campus Construction Progress - 15.07.2022
Campus Construction Progress - 02.07.2022
Campus Construction Progress - 14.05.2022
Campus Construction Progress - 28.04.2022
Campus Construction Progress - 15.04.2022
Campus Construction Progress - 26.03.2022
Campus Construction Progress - 17.03.2022
Campus Construction Progress - 01.03.2022
Campus Construction Progress - 12.02.2022
Campus Construction Progress - 26.01.2022
Campus Construction Progress - 11.01.2022
Campus Construction Progress - 01.01.2022
Campus Construction Progress - 15.12.2021
Campus Construction Progress - 30.11.2021
Campus Construction Progress - 14.11.2021
Campus Construction Progress - 30.10.2021
Campus Construction Progress - 14.10.2021
Campus Construction Progress - 29.09.2021
Campus Construction Progress - 07.09.2021
Campus Construction Progress - 23.08.2021
Campus Construction Progress - 09.08.2021
Campus Construction Progress - 30.07.2021
Campus Construction Progress - 15.07.2021
Campus Construction Progress - 30.06.2021
Campus Construction Progress - 20.06.2021
Campus Construction Progress - 05.06.2021
Campus Construction Progress - 20.05.2021
Campus Construction Progress-05.05.2021
Campus Construction Progress - 22.04.2021
Campus Construction Progress - 06.04.2021
Permanent Campus Site Visit by the Director - 18.03.2021
Campus Construction Progress - 17.03.2021
Campus Construction Progress - 03.03.2021
Campus Construction Progress - 19.02.2021
Campus Construction Progress-05.02.2021
Campus Construction Progress-08.01.2021